Scheduling Conflicts
A conflict occurs when two schedule blocks overlap on the same line. RunMark warns you about conflicts but allows you to save them — you remain in control.
Why conflicts happen
- A run takes longer than expected and bleeds into the next block
- A block was moved without checking what's already there
- Two runs were scheduled back-to-back with no changeover buffer
Resolving a conflict
Move one block to a different time. Click the conflicting block on the Gantt, open the detail panel, and reschedule it to a non-overlapping time slot.
Move one block to a different capable line. If another line can run the same SKU, reschedule the conflicting block there. Check the line's capability list in Lines settings.
Delete and recreate. If a block belongs to an order you can reschedule freely, delete the block from the Gantt and use the Orders page to re-schedule it.
Preventing conflicts
- Leave a changeover buffer between back-to-back jobs on the same line by setting accurate changeover times in the line configuration.
- After scheduling a block, check the Gantt view before adding the next block on the same line.
- Ask the Production Assistant: "What's scheduled on Line 1 this week?" to see what's in the queue before scheduling.